During the months of February and March 2016, the following construction activities will occur:

  • Electrical equipment will be hoisted up to the hospital roof in front of the Emergency Department on Tuesday, February 9 and Sunday, February 14, 2016.
  • Underground communication lines will be installed along the patient drop off area at Bingham Street.
  • Roadwork on a new vehicle lane will also occur between the parking garage and newly constructed building.
  • Generator building construction continues in the private lane.
  • Drills, jackhammers and saw cutters will continue to be used throughout the day.
  • There may be some congestion in the private fire lane and driveway as the construction of the generator building continues and construction trucks come in and out.
  • Drivers using Bingham Street should expect some delays, as construction and commercial trucks will be in the area to haul away debris and delivering supplies/construction materials.
  • There may be some congestion at the patient drop-off area. Staff will be on hand to assist patients and families.

We apologize for any inconvenience

We apologize for any inconvenience and appreciate your continued support as we build a new hospital for Hawaii’s keiki. 

Should you have any concerns or questions about our construction project, please call our construction information line at 808-535-7669.


Construction Hours

Monday through Friday: 7 a.m. - 6 p.m. 
Demolition (using jackhammer, saw cutting, etc.) 9 a.m. – 5:30 p.m.

Saturday: 9 a.m. - 6 p.m.
There will be a break in construction during the midday when the crew stops for lunch.


For information, call the construction information hotline at 808-535-7669, or visit our Facebook page at www.facebook.com/kapiolanimedicalcenter for the latest updates.

Your Support Makes a Difference

Donate Now

Learn More About Giving »

Media Contact

Liz Chun Uyehara
Liz.Uyehara@HawaiiPacificHealth.org
808-535-7675